NTPC Green Energy Adds 95.6 MW from Kalasar Solar Project in Rajasthan

NTPC Green Energy has commissioned another 95.6 MW at its Kalasar Solar Project in Rajasthan, marking the fifth phase of the 650 MW solar component linked to the REMCL RTC project.

  • Company – NTPC Green Energy Limited
  • Project – Kalasar Solar Energy Project
  • Location – Bikaner, Rajasthan
  • Commissioned Capacity – 95.6 MW
  • Solar Component – 650 MW
  • Associated Project – 500 MW REMCL RTC Project
  • Commissioning Date – 30 October 2026
  • Commissioning Phase – Fifth Part Capacity
  • Group Installed Capacity – 11,424.29 MW

NTPC Green Energy Limited (NGEL) has commissioned the fifth part capacity of its Kalasar Solar Energy Project in Bikaner, Rajasthan, adding 95.6 MW to its renewable energy portfolio.

The latest commissioning milestone increases the NTPC Green Energy Limited group’s total installed capacity to 11,424.29 MW, strengthening its renewable energy generation portfolio.

NTPC Green Energy Commissions Fifth 95.6 MW Part of Kalasar Solar Project in Rajasthan

NTPC Green Energy Limited (NGEL) has announced the commercial operation of the fifth part capacity of its Kalasar Solar Energy Project in Bikaner, Rajasthan, adding 95.6 MW of solar power capacity to its renewable energy portfolio.

The newly commissioned capacity became commercially operational with effect from 00:00 hours on October 30, 2026. The project is being implemented by NTPC Renewable Energy Limited, a wholly owned subsidiary of NTPC Green Energy Limited.

The 95.6 MW capacity forms part of the 650 MW solar component being developed under the 500 MW Round-the-Clock (RTC) renewable energy project associated with Renewable Energy Management Company Limited (REMCL).

Kalasar Solar Project Progresses Through Multiple Phases

The latest commissioning represents the fifth part of the Kalasar Solar Energy Project. According to NGEL’s official project announcements, the company has progressively declared the following capacities commercially operational:

Commissioning phaseCapacityEffective date
First part81.34 MW26 September 2026
Second part73.06 MW1 October 2026
Third part80.88 MW1 October 2026
Fourth part66.18 MW10 October 2026
Fifth part95.60 MW30 October 202
Total397.06 MW

With the latest addition, the cumulative capacity declared across these five commissioning phases reaches 397.06 MW of the 650 MW solar component.

Also Read NTPC Largest Wind Energy Project :- NTPC Green Energy Commissions 50.4 MW of Jamjodhpur Wind Project in Gujarat

NTPC Green Energy Group Capacity Update

Following the commissioning announcement, NTPC Green Energy Limited reported that its group’s installed capacity increased from 11,328.69 MW to 11,424.29 MW.

The company also reported a current commercial capacity of 11,328.69 MW in its disclosure. These are two separate capacity figures and should not be treated as interchangeable.

The development reflects NTPC Green Energy’s continued progress in expanding its renewable energy portfolio through large-scale solar projects in Rajasthan and other renewable energy-rich regions of India.

The Kalasar project is another milestone in NTPC’s renewable energy expansion strategy and contributes to the development of solar generation capacity linked to round-the-clock renewable power supply.